Bidding
All projects over $50,000.00 must be advertised and competitively bid. The Purchasing division of the Department of Administrative Services and the project manager will invite contractors to a pre-bid meeting on the job site and present the project in detail. Contractors will typically have 3 1/2 weeks to prepare and submit their bids. Contractors may, by going through HCFD, revisit the site during this phase and ask for clarification of the bid documents. Questions about the bidding process should be directed to the project manager.
Bid Approval
If department funded, after the Purchasing division and the project manager have reviewed the bids, the total project cost will be presented to the requestor for approval. Every effort is made to include all costs associated with the project. The requestor is responsible for developing and requesting project authorization for the full cost of the project.
Building Permit Application
Building permits must be taken out for most projects. The contractor will most often file the permit application and handle all interactions with the City of Cincinnati's or the other applicable local building department for small projects. On major projects, the architect/engineer will apply for permits at the time of bidding. Only preparatory work (site preparation, work trailer installation, etc.) can start before receipt of a building permit. Contractor picks up permit when ready. Contractor responsible for payment.
Write/Sign/Process Contract Documents
The Purchasing division will issue both a contract and a purchase order, which is a binding contract, with the contractor. No work will be started until a contract is executed and a purchase order is in place. The contract must be signed by the contractor, reviewed by the project manager and County Prosecutor, and signed by the Director of County Facilities and the County Administrator, depending on the contract amount. Following approval of the contract, a purchase order will be issued to the contractor, along with a contract.
Construction
The duration of construction varies with the scope of the work. During this work only contractors and project managers are allowed on the construction site, due to the legal liabilities of the contractors.
Punch List
When a construction project is approximately 95% complete, a list of deficiencies, called a "punch list", will be generated by the project manager. These items must be corrected prior to HCFD accepting the work as complete. The time allotted for correcting these deficiencies varies with the scope of the work.
Final Inspection & Occupancy Permit
All permitted projects must have a final inspection by the City of Cincinnati or local/state building department. When the building inspector is satisfied that the work is complete and in compliance with all applicable building codes, an occupancy permit will be issued. Under no circumstances may a space be occupied prior to receipt of an occupancy permit or a partial occupancy permit.
Occupancy
Occupancy is the date that HCFD accepts the project space from the contractor.
Project Closeout
At the completion of a project, the project manager must collect and compile all project documents for filing. These include all warranties, guarantees, waiver of liens, maintenance manuals, contract documents, permit drawings and specifications, as-built drawings, test reports, meeting minutes, change orders and partial payment requests.